According to the Gauteng Provincial Department of Health,
a) The project of refurbishing the eight (8) wards as, indicated in the response to Question 2743 by Ms N Chirwa was successfully completed and the wards are fully operational. Below are the dates of occupation achieved for each of the wards:
Ward 1: 13 July 2020
Ward 2: 08 July 2020
Ward 3: 31 July 2020
Ward 4: 28 August 2020
Ward 5: 13 July 2020
Ward 6: 08 July 2020
Ward 7: 28 August 2020
Ward 8: 28 August 2020
b) The refurbishment project was done at a cost of R186,000,000.
END.