a) The Department has not yet built Silulu Secondary School but conducted planning and design in the 2018/19 Financial year and earmarked construction commencement in the 2019/20 and completion in the 2020/21 financial year. The Project was out on tender in May, however was withdrawn and will be re-advertised in the 4th quarter of the 2019/20 Financial Year.
b) The estimated total project cost is R63 250 000.