- The purpose of the project was to provide FIFA with a training venue as a guarantee for the 2010 World Cup. - The budget for the project was R31,000,000. - The project duration was from 19 June 2009 to 20 May 2010 (49 weeks). - Project description: Pitch works including pitch barrier fence, civil works including paving and aggregate surface, building works, i.e. change rooms and ablution block including tunnel and main entrance, Stadium lights, remedial works to boundary wall, reinstating of the athletics track and supply of domestic water and irrigation tanks. - Fifty nine labourers were employed on the project, including eight in bricklaying, three in administration and two in carpentry. - Training was provided as follows: 11 in bricklaying, 3 in welding, 7 in pitch laying, 6 in electricity installation and lighting, 5 in plumbing, 2 in carpentry, 16 in paving, 12 in tiling, 7 in glazing and 72 in occupational health & safety.