1. (a)(b)(i) and (ii): The Small-scale Embedded Generation (SSEG) rules will be finalized once the notice of exemption from licensing has been gazetted by the Department of Energy. Gazetting of the exemption notice will happen once the opinion of the Office of the State Law Advisor on the exemption notice is obtained.
2. No, in the absence of an enabling legal and regulatory framework NERSA can neither license nor register SSEGs like Roof Top Photovoltaic. Generator installations up to 100kVA are exempted from being regulated, in terms of Schedule 2 of the Electricity Regulation Act.
3. We are not aware of Eskom’s net-metering programme. Municipalities may have a different regime due to their Constitutional mandate pertaining to electricity reticulation.
4. We are not aware of Eskom’s net-metering programme.