With reference to the cost of (a) Medupi that stands at R86.5 billion from R49.8 billion and (b) Kusile that stands at R83 billion from R57 billion but neither of which are near completion, what are the reasons that Eskom’s finance cost for the current financial year has increased with 82% whereas the specified amount excludes all the capitalised finance cost for work construction, like Medupi, Kusile and all other projects that are still under construction?