a) The planning for the Tsitsikamma restaurant precinct development has been completed following the fire in November 2016 and is ready to be subjected to a tender process. After the restaurant was destroyed by the fire, SANParks decided to upgrade the entire restaurant precinct to include all infrastructure.
The project scope includes the following:
b) It is envisaged that the tender and contracting process will take six months from May 2018 to October 2018. Construction is scheduled to commence in January 2019 after the peak tourism season. The estimated construction period is 18 months due to the difficult site and visitor management requirements, with estimated completion in September 2020.
The clients are being serviced from provided marquee since 10th December 2016