SHORT-TERM INTERVENTIONS
MEDIUM-TERM TO LONG-TERM INTERVENTIONS
2. The preliminary network analysis that has been conducted reveals that 25 hospital in various provinces can be excluded from loadshedding by building new infrastructure at the indicative cost of approximately R101 million rand. For hospitals deeply embedded in the Municipalities networks, Eskom will support the Department of Health in exploring possible options and can offer containerized PV(PhotoVoltaics) solutions where possible.
3. The National Department of Health in partnership with CSIR (Council for Scientific & Industrial Research) is currently conducting a due diligent exercise for the installation of solar panels at all our health facilities as a first or second or third power back-up mechanism (first being generators; second being solar panels; and third being Uninterrupted Power Suppliers). This due diligent exercise is inclusive of solar PV + battery storage as backup for the critical areas of the following hospital types based on an estimated demand profile
The purpose of the study is to identify a critical consumption for critical areas of each health facility so that the department can be able to roll-out the relevant solar energy for each health facility.
END.