1. (a) The National Department of Health has received 306 generators.
(b) 34 generators per province. In order to meet the minimum demand for each clinic, it’s going to be two generators per clinic. 6KW x 2 = 12KW. Therefore, it’s going to be 19 clinics earmarked for the generators.
2. (a) The National Department of Health is currently finalising the procurement process. The procurement process covers both the collection and installation of the generators directly to the main electrical distribution board of the clinics.
(b) (i) The details of the Service Providers will be provided after the completion of the procurement process.
(ii) the total cost will also be provided after the completion of the procurement process.
3. The National Department of Health will ensure that there is enough budget allocation for the fuel consumption of generators across the country. Currently, there is no fuel expenditure on these new generators.
4. (a) None installed yet.
(b) 306 to be installed.