To begin with Honourable member, it is important to note that the RDP houses were discontinued when Cabinet adopted the Comprehensive Plan for the Development of Sustainable Human Settlements in 2004 setting new standards for housing typologies for government houses referred to as BNG houses.
The total number of incomplete units in the Mogalakwena Local Municipality is 319 houses spread over a total of 14 villages. The Limpopo Provincial Department of Co-operative Governance, Human Settlements & Traditional Affairs has appointed Contractors in 2019/2020 to complete 210 units. It is expected that the units will be completed by the end of October 2020. The Provincial Department will appoint Contractors during the 2021/22 financial year to complete the remaining 109 units. The anticipated completion date is 31 March 2022.
The total number of incomplete units in the Makhado Local Municipality is 87 spread over a total of 11 villages. The Limpopo Provincial Department of Co-operative Governance, Human Settlements & Traditional Affairs will appoint Contractors in the 2021/2022 financial year to complete the 87 units. The anticipated completion date is 31 March 2022.