Based on the information provided by the Kwa-Zulu Natal Provincial Department of Human Settlements, the project is at a pre-feasibility stage. An application was received by the Provincial Department of Human Settlements from eThekwini Metropolitan Municipality, which was duly processed and feedback was accordingly provided to the Metropolitan Municipality. The eThekwini Metro is currently incorporating all the comments received from the Provincial Department of Human Settlements, to ensure that the project meets the funding criteria for the Human Settlement Development Grant (HSDG).
The table below provides the timeframes and envisaged dates for the execution of project tasks which includes the construction of houses.
Activity |
Time Frame |
Approval of project implementation funding |
February 2021 |
Detailed planning studies |
October 2019 - June 2021 |
Pre – Implementation Submission Consultations |
April 2021 |
Final planning application submission |
May 2021 |
Planning approval |
June 2021 |
Submission and approval of Tranche 2 application to Provincial Department |
July – September 2021 |
Installation of Services |
October 2021 - March 2022 |
Top structure construction |
April 2022 |