The Ncora Regional Bulk Infrastructure Project, which is funded by the Department of Water and Sanitation (DWS) in terms of the Regional Bulk Infrastructure Grant (RBIG), has been completed and bulk supply lines have been installed in the Ncora zone areas that feed wards 17, 18 and 19.
Components of the projects that are outstanding comprise of the villages’ internal reservoirs and reticulation which is funded through the Municipal Infrastructure Grant (MIG) funding from the Department of Cooperative Governance (CoGTA). Progress can be summarised as follows:
CHDM CLUSTER 4 NCORA ZONES |
|||||
WARD |
Village Names |
Population |
Completed |
Duration |
Comments |
WARD 19 |
Gcina-K |
935 |
Completed |
|
Supplied from the Ncora Water Treatment Works. Rehabilitation of existing reticulation required. |
Maqwathini-C |
739 |
Completed |
|
||
Mqanqeni |
951 |
Completed |
|
||
KwaMqanqeni |
1 283 |
completed |
|
||
Maqwthini-A |
1 613 |
Completed |
|
||
Nquqhu-B |
1 954 |
Completed |
|
||
Nonqonqwama |
2 093 |
Completed |
|
||
Ngxabangu |
2 308 |
Completed |
|
||
Dipini-A |
1 013 |
Completed |
|
||
Hoyana |
1 115 |
Completed |
|
||
Taiwan |
181 |
Completed |
|
||
eQolweni-A |
452 |
Outstanding |
32 weeks |
Technical reports ready. Awaiting budget allocation. Supplied from Ncora Treatment Works. |
|
Halla BB |
418 |
Outstanding |
32 weeks |
||
Mtinwevu Mission |
340 |
Outstanding |
40Weeks |
||
Mpunga & Nquqhu |
421 |
Outstanding |
40 Weeks |
||
Sub Total |
|
14 185 |
|
|
|
WARD18 |
Banti |
673 |
Completed |
|
Supplied from the Ncora Water Treatment Works. Under ConstructIon |
Mahlungulu-C |
683 |
Completed |
|
||
Gongqo |
1 854 |
Completed |
|
||
Kwachotha |
1 292 |
Outstanding |
28 weeks |
Design Ready, CHDM to finalise Budget allocation |
|
Nomadambe |
903 |
Outstanding |
43 weeks |
||
Nomadamba |
1 302 |
Outstanding |
56 weeks |
||
lahlangobo-D |
465 |
Outstanding |
24 weeks |
||
Longqayi |
883 |
Outstanding |
43 weeks |
||
Lower Ncora |
783 |
Outstanding |
43 weeks |
||
Jojweni-N |
2 754 |
Outstanding |
|
||
Sub Total |
|
11 592 |
|
|
|
WARD 17 |
Melika |
832 |
Completed |
|
Supplied from the Ncora Water Treatment Works. Village Reticulation completed. |
Luqolweni |
112 |
Completed |
|
||
KwaMzola |
3981 |
Under Construction |
80 Weeks
|
Immediate Future Supply from the Ncora Water Treatment Works. Village reticulation and 12km of secondary bulk line still to be implemented. CHDM busy with procurement and funding prioritisation. |
|
Luqolweni-F |
215 |
||||
Matafeni - B |
279 |
||||
Pesikeni |
811 |
Outstanding |
56 weeks |
||
Mqwazini |
320 |
Outstanding |
36 weeks |
||
Matafeni - A |
692 |
Outstanding Tender doc Ready |
|
||
Mgababa- A |
1495 |
Outstanding |
26 weeks |
||
Gesini |
371 |
Outstanding Tender doc Ready |
43 weeks |
||
Esigangeni-A |
816 |
outstanding |
43 weeks |
||
Bhotani-A |
543 |
outstanding |
36 weeks |
||
Tshayelela |
455 |
outstanding |
24 weeks |
||
Bhotani-A |
543 |
outstanding |
36 weeks |
||
Bhotani-B |
857 |
outstanding |
43 weeks |
||
Home |
209 |
outstanding |
24 weeks |
||
Sub Total |
12 531 |
|
|
|
|
Grand Total |
|
38 308 |
|
|
|