(a) The average time for construction of a government-subsidised house is 35 days.
The breakdown is as follows:
• Preparation of foundation and casting: 7 days
• Brick work: 3 days
• Roofing: 2 days
• Plumbing: 4 days
• Plastering: 3 days
• Painting: 1 day
• Glazing: 1 day
• Turnaround time for inspection by the Engineer; the Provincial Department of Human Settlements and the Municipality: 7 days
• Preparation and key handover: 7 days
(b) The average time for construction of a government-subsidised house in Savanna City has been 35 days.
(c) The total number of houses completed to date is 2 434 which comprises of 1 492 subsidised houses, 90 Financed Linked Individual Subsidy Programme (FLISP) houses and 352 bonded houses.