The Department of Human Settlements:
(a) & (b) The amount spent by the Department of Human Settlements on purchasing and installation of a generator is R1 784 859,00.
(c) The amount for operating costs (fuel) since the generator was purchased R 22 956.00.
(d) There are no maintenance costs incurred thus far.
The Entities:
(a) There are eight (8) public entities reporting to the Minister of Human Settlements, only the following three public entities have purchased generators:
(b) Installation cost for the generators of NHBRC and NURCHA was included in the purchasing amount. EAAB has spent R 10 000.00 for installation.
(c) Spending on operational cost, including fuel:
(d) Maintenance of generators