According to the information received from ESKOM
During the recent oversight visit by the Standing Committee on Public Accounts to Kusile Power Station, Unit 1 was on forced outage. The unit has since been repaired and it is back on load. The commercial process to establish the Operating and Maintenance Contract with Technical Support that will assist in restoring the reliability of the plant, as well as providing Kusile with skills development, is underway.
Flue Gas Desulphurisation has not yet been installed at Medupi Power Station, and when it is, the learnings from Kusile will be incorporated into the Operating and Maintenance processes.