(1) The insurance claim has not yet been concluded and no money has been paid out.
(2) Not applicable as no money has been paid to Eskom.
(3) The Duvha Unit 3 Recovery Project execution strategy has not yet been approved by the Eskom Board. Only preservation and site preparation work has commenced. Timelines into recovery will only be definite once a service provider has been appointed.
(4) The relevant stakeholders will be kept abreast of these developments as required.
END