The Minister of Public Works and Infrastructure:
(1)
(a) The number of completed structures were not recorded on 29 July 2022. However, they were recorded during a count carried out by the Sheriff of the Court in August 2022 as 4880.
(b) No further demolitions were carried since February 2022.
(c) The number of structures were not recorded at the end of the security company’s contract. However, they were recorded in August 2022 as 4880.
(2)
(a) The number of completed structures were not recorded when the security took over.
(b) There were no further demolition of structures since February 2022.
(c) The number of completed structures were not recorded on 29 September 2022. However, they were recorded during a count carried out by the Sheriff of the Court in August 2022 as 4880.