The Minister of Public Works and Infrastructure:
1.
a) Number of Applications received |
b) Progress of each application |
C Full details in terms of |
||
(i) Applicant |
(ii) timelines |
(iii) Additional Information |
||
3 |
This application has progressed through the Agrément South Africa evaluation process. Status: The application is at the final stages of evaluation, pending confirmation from the client for a site/factory visit in the USA. |
Black Lion Capital |
End of March 2024. |
ASA will reach out to the client to finalise the anticipated site visit. |
Progress: The application is stalled at the application review phase. Reason: The client wants to further develop their system. |
SMACT Building systems |
The timeline is dependent on the client’s response. |
After the peer review of the application by ASA assessment team, questions were sent SMACT, and we are still waiting for their response. |
|
Progress: The application is at the assessment work offer phase; the contract of assessment is currently with the client according to Agrément South Africa records. Status: The assessment work offer was sent to the client and has elapsed without the client’s approval; revision of the assessment work offer would be required to proceed with the project |
RevCon Technologies |
The timeline is dependent on the client’s response. |
The initial offer was sent to RevCon on the 22/01/2020, which was not accepted by the client and it has lapsed. |
2. Indicate if any ASA employee or board member is:
(a) An employee of the applicant/s |
(b) members of the board of the applying organisation / company |
(c) have any links with the companies that have applied |
None |
None |
None |