The Minister of Public Works and Infrastructure:
I have been informed by the Department that:
a) The intended handover of phase 1 of the renovations is 03 May 2024
b) (i) The available budget for Phase 2 is R 51,828,205.97
(ii) The intended time frame for completion of Phase 2, is 14 months with the anticipated completion date for Phase 2 is planned for 30 March 2026
c) The total amount allocated for the entire project since inception is R 82,766,187.19
d) The Implementing Agent for the project is the Development Bank of Southern Africa (DBSA)