1.a) The company contracted to construct the ICT2 Building was Stefannuti Stocks/Timbela Joint Venture.
b) i) The site for the construction was handed over on 23 January 2011. The ‘Works Completion’ was on the 6 December 2011.
ii) The ‘Final Completion/Correction of Defects’ was on 5 December 2012. The official opening of the ICT2 building was on 29 November 2011 and official occupation was on 2 January 2012.
2.a) Occupation of the ICT2 building took place on the 2 January by the CAV staff and by Aerosud.
b) Aerosud and the CAV staff still occupy the building which is mainly used for innovation and training for the Ahrlac programme.
3.a) Electricity, water and sewer services to the ITC2 building was supplied by Aerosud from the commencement of construction as a temporary measure. This was also the case with respect to the provision of electricity to the construction activities for phase two of the CAV.