(a)(i) & (ii) The Mpumalanga and Limpopo sections of Moloto road (R573) were transferred to SANRAL in July 2015. At the time SANRAL indicated to National Treasury that the timelines are severely dependent on the regulated procurement, design and land acquisition processes to be followed by SANRAL, running according to plan.
On the Mpumalanga section a Consulting engineering firm was appointed in February 2016 and in March 2016 for the Limpopo section, for design and supervision of the construction contracts.
Due to the urgency in addressing the safety concerns on the route, a process to accelerate the works was initiated. To this end, one construction project in Mpumalanga and Limpopo, each, commenced in January 2017, where the delays of regulatory requirements were limited.
MOLOTO ROAD PROJECT |
2016/17 |
2017/18 |
2018/19 |
2019/20 |
Totals |
R’ 000 |
R’ 000 |
R’ 000 |
R’ 000 |
R’ 000 |
|
Budget |
R 660 834 |
R 1 279 029 |
1 806 813 |
1 691 990 |
5 438 660 |
Transfer to date |
R 660 834 |
R 639 515 |
n/a |
n/a |
R 1 300 380 |
Table 1: Summary of SANRAL Budget Allocations and Expenditure
(b) The Gauteng section of the R573 Moloto road is not transferred to SANRAL. SANRAL and Gauteng Province signed an implementing agent agreement, in which the funding for the design, land acquisition and construction is provided by the Gauteng Province. To date, the Province has not been able to secure the funding and therefore construction has not started.
The under-expenditure is therefore only on the Gauteng Provincial section of the Moloto Road.
(c)(i) The section of the project under SANRAL’s jurisdiction is not behind schedule, however the following challenges exist:
(c)(ii) None.
(d) (i) Extensive engagement with stakeholders i.e. Local and Tribal Authorities, Land Occupiers and Service Providers.
(ii) Community Participation – Setting up of Public Liaison Committees (PLCs), appointment of the Project Liaison Officers (PLOs) and recruitment processes, which involves setting up databases for labourers and sub-contractors; and selecting labourers through the raffle methods in their Wards (32 in Mpumalanga). All these processes need to be completed prior to any construction works commencing.
(iii) Workshops for SMME’s and prospective contractors and sub-contractors.