(b) (i) 22 February 2017
(ii) A date has not been set since the new contractor has not yet been appointed due to unresolved matters with National Treasury. A total of ten months is required to complete the works.
(2) (a) (i) R15 678 620.13 (Excl. VAT)
(ii) For nine months from February 2018 until October 2018, a total of R 562,962.00 (Excl. VAT)
(iii) Latest estimate R65 764 304.37 (Excl. VAT)
(b) As the construction company has been liquidated, the Performance Guarantee to value of R5.7 million was paid by the guarantor to SANRAL for the non-performance by the contractor in fulfilling his obligations to complete the contract.
3. As indicated the company Nyoni Projects (Pty) Ltd has been liquidated and are no longer in existence.