Key programmes on the rail infrastructure network is reflected in the table below. All of these projects are multi-year projects and dates indicated on current projects are as per contracts.
Plans/Programme |
Region |
d) Key Milestones |
b &c) Projected Completion Date |
e) Monitoring Mechanism |
Re-Signalling Programme |
KwaZulu/Natal (KZN) |
25 Jun 2021 |
Project Progress meetings; Monthly report; APP; Quarterly Report DOT |
|
Phase 1: Pinetown line |
20 Jul 2018 |
|||
Phase 2: New Rossborough Centralised Traffic Control Centre (CTC) |
16 May 2019 |
|||
Phase 3A: Kwa Mashu to Temple |
30 Nov 2018 |
|||
Phase 3B: Avoca to Springfield |
27 May 2020 |
|||
Phase 4: Umlazi to Umbogintwini |
23 Sep 2019 |
|||
Phase 5: Clairwood to Crossmoor |
05 Jun 2020 |
|||
Phase 6: Berea to Congella |
15 Oct 2020 |
|||
Phase 7: Durban station |
11 May 2021 |
|||
Western Cape (WC) |
30 Jun 2020 |
Project Progress Meeting ; Monthly report; APP Quarterly report to DOT |
||
Regional Monitoring and Train Control Centre (RM&TCC) |
30 June 2018 |
|||
Phase 1.2: Wynberg – Simonstown, Crawford – Diep River |
30 Apr 2018 |
|||
Phase 1.4: Koeberg – Maitland - Hazendal |
31 May 2018 |
|||
Phase 1.3: Salt River - Kenilworth |
31 Jul 2018 |
|||
Phase 3.1: Cape Town - Woodstock (South) |
30 Sep 2018 |
|||
Phase 3.2: Cape Town - Woodstock (North) |
31 Oct 2018 |
|||
Phase 2.3: Esplanade - Ysterplaat |
31 Jan 2019 |
|||
Phase 1.1: Philippi - Kaptiensklip, Chris Hani |
28 Feb 2020 |
|||
Phase 2.2: Woltemade – Parow |
31 Mar 2020 |
|||
Phase 2.1: Langa - Nyanga, Bontheuwel – Sarepta |
30 Apr 2020 |
|||
Phase 4.1: Tygerberg – Bellville |
31 May 2020 |
|||
Phase 4.2: Kuils River - Strand, Eerste River - Muldersvlei |
30 Jun 2020 |
|||
Gauteng |
28 Feb 2021 |
Project Progress meetings; Monthly report; APP; Quarterly Report DOT |
||
Gauteng Nerve Centre (GNC) |
Apr 2016 - Completed |
|||
Phase 1: Midway – Residentia |
31 Mar 2016 – Completed |
|||
Phase 2: Kaalfontein – Leralla, Olifantsfontein – Irene |
28 Nov 2016 – Completed |
|||
Phase 3: Randfontein – Roodepoort |
15 May 2017 – Completed |
|||
Phase 4: Boksburg East – Springs, Daveyton – Alliance |
15 Dec 2017 – Completed |
|||
Phase 5: George Goch – Geldenhuys, Benrose – Kaserne West, Booysens – Crown |
03 Apr 2018 |
|||
Phase 6: Rissik – Koedoespoort – Eerste Fabrieke |
15 Dec 2019 |
|||
Phase 7: Jeppe – Johannesburg – Braamfontein |
25 Sep 2018 |
|||
Phase 8: Centurion – Pretoria, Mitchell Street – Saulsville |
07 Jan 2019 |
|||
Phase 9: Kempton Park – Knights |
11 Mar 2019 |
|||
Phase 10: Langlaagte – Florida, Croesus |
20 May 2019 |
|||
Phase 11: New Canada – Naledi, Orlando – Kliptown |
14 Oct 2019 |
|||
Phase 12: Hercules – Belle Ombre, Capital Park East and West, Pretoria North – Mabopane, Rosslyn |
23 Jun 2020 |
|||
Phase 13: De Wildt |
06 Jul 2020 |
|||
Phase 14: Driehoek – Germiston, Angelo – Oosrand, Kutalo – Elsburg – Kwesine, India |
01 Feb 2021 |
|||
Blue Downs Rail Extension |
Western Cape: Cape Town |
Preliminary Design and EIA Detail Design Construction Operations Aim to commence Preliminary Design in 2018/19, thereafter timeframes can be confirmed with greater accuracy. Allow for 4-6 month procurement process for phases leading up to Operations |
12 – 15 months 6 months
|
Programme Management office Cape Town Intermodal Planning Committee |
Depot Modernisation Wolmerton |
Gauteng North |
Phase 1 complete Phase 2 in testing & commissioning scheduled for completion by end March 2018 Phase 3 Consultants appointed Designs complete Contractor appointed All construction complete |
February 2019 February 2020 November 2021 March 2026 |
|
Depot Modernisation Braamfontein |
Gauteng South |
Will be done in phases Phase 1 awaiting appointment of contractor by PRASA Board. 12 month design and construction period envisaged Phase 2 Consultants appointed Designs complete Contractor appointed All construction complete |
June 2019 March 2020 December 2021 June 2024 |
Project Progress meetings; PRASA Tech Management Committee; Monthly report; APP; Quarterly Report DOT |
Depot Modernisation Salt River |
Western Cape |
Will be done in Phases Phase 1 will be advertised by June 2018 and construction will be complete by June 2021 Phase 2 Consultants appointed Designs complete Contractor appointed All construction complete |
December 2019 December 2020 December 2021 June 2025 |
PRASA Tech Management Committee; Monthly Report; APP Quarterly Report DOT |
Depot Modernisation Durban Yard and Springfield |
KZN |
Consultants appointed Designs complete Contractor appointed All construction complete |
January 2019 January 2020 November 2021 March 2026 |
PRASA Tech Management Committee; Monthly Report; APP Quarterly Report DOT |