1. (a) SANRAL followed a tender process for the overall toll system design, build and operations thereof in 2009 in accordance with the SCM requirements at the time.
(b) Following this tender process, it appointed ETC Pty Ltd as the successful tenderer.
(c)This tender included the collection of outstanding e-Toll debt. This was revised to address the New Dispensation announced by the Deputy President, with specific reference to the 60% discount offering in respect of historic debt. ETC is therefore responsible for the collection of e-toll debt and may appoint parties to attend to this on their behalf. SANRAL only contracts (in terms of its Contract with ETC) with ETC and not directly with the 3rd party.
2. As stated, SANRAL only has an agreement with ETC Pty Ltd. There is therefore no "specified tender" by SANRAL in relation to the so called "unpaid e-toll bills" and in respect of which the question appears to be addressed. ETC is responsible for the collection of debt for the contract period. SANRAL appointed ETC in 2009, as explained above.