(1) The KwaZulu-Natal (KZN) province is the only province with approved Business Plan and dedicated budget for drought interventions thus far, refer to Annexure A. All other provinces are using funds which are reprioritized/adjusted within the Departmental budget.
(2) Refer to the table below for the specified provinces declared drought areas.
Province |
Date Declared |
Type of Declaration |
KwaZulu-Natal |
17 December 2014 |
Old declaration, Provincial Gazette 167 |
8 February 2016 |
Updated declaration to include 2 additional Municipalities, Provincial Gazette No 1600. |
|
North West |
24 July 2015 |
Provincial Gazette 7501 |
Free State |
4 September 2015 |
Provincial Gazette 83 |
Limpopo |
13 November 2015 |
Provincial Gazette 2630 |
Mpumalanga |
04 December 2015 |
Provincial Gazette 2619 (Not all local municipalities in the DM) |
Western Cape |
25 November 2015 |
Council Resolution |
Eastern Cape |
4 December 2015 |
Provincial Gazette 3560 Ugi Town declared a Local State of Organic Pollution |
22 January 2016 |
Provincial Gazette 3582 Council Resolutions in the following DMs: OR Tambo on 11 Jan 2016, Alfred Nzo on 17 Dec 2015. |
|
04 March 2016 |
Extension, including Ugu Town Provincial Gazette 3606. |
|
Northern Cape |
29 January 2016 |
Provincial Gazette 1983 |
(3) (a)Restrictions for Dams are applied starting from different levels for different Dams as per the Dam’s operating rules to prevent the Dams from complete failure to supply water or to prolong water supply from each Dam provided the restrictions are adhered to. For additional information on Dam Levels kindly refer to https://www.dwa.gov.za/Hydrology/Weekly/ProvinceWeek
(3)(c) No applications were received for further abstraction past the restricted level.
(3)(d) Not Applicable (N/A).
(3)(e) Annual Operating Analysis is conducted each year at the end of the rainy season to determine allocable amount for the particular year.
(4) Requesting Honorable Member to refer to NA 428 on February 2016 as this question was adequately responded to.