(1)(a)(i) There is no amount of funding that has been allocated to Maluti-a-Phofung Local Municipality in the 2015-16 financial year.
(1)(a)(ii) There is a total amount of R15,000,000 that has been allocated to Maluti-a-Phofung Local Municipality in the 2016-17 financial year.
(b) The total amount of R15,000,000 has been allocated to Maluti-a-Phofung Local Municipality since 1 April 2017.
(2)(a) A total of 60 Boreholes are intended for development over a multi-year phased approach through Sedibeng Water as the Implementing Agent.
(2)(b) A total of 55 Boreholes have been drilled.
(2)(c) All work on the ground and payments made to date has been verified.