Refer to Annexure A for the names, amounts, delays and cost of the specified projects affected by non-approval of rollover from 2014/15.
Although the non-approval of the rollover had a negative impact on the cash flow for projects, my Department had to reprioritise within projects, whereby funds were shifted from slow moving projects, to those projects affected by non-approval of the rollover to avoid delays and cost escalations. The available budget was spent in full for the 2015/16 financial year.