(1)(a) The project was approved as a Government water work on 8 June 2010.
(1)(b)(i) The approved budget is R593 million.
(1)(b)(ii) The Expenditure as at August 2016 is R233 million.
(1)(c) The expected completion date is January 2018 (revised per programme).
(1)(d) The expected completion cost is R620 million (revised).
(2) Yes, the project went out on tender.
(2)(a) Below are the names of the companies that made submissions for the tender:
BIDS RECEIVED |
|
1. |
Bicacon PTY/Mapitsi Civils/Setheo Consortium & SinoHydro Joint Venture (JV) |
2. |
Lubbe Construction |
3. |
Aveng Grinaker |
4 |
Basil Read LTD/ Rodio Consortium |
5. |
MRC – DSB Consortium |
6. |
Group Five Coastal (PTY) LTD |
(2)(b)
The name of the company that was awarded the tender is Group Five Coastal (PTY) LTD.