Refer to the table below:
(a)(i) Name of Waste Water treatment plant |
(a)(ii) (aa) Sewerage pipelines upgrade |
(a)(ii) (bb) Sewerage pipelines refurbished |
(b) Due date for specified improvements to begin |
(c) Allocation through MIG |
Emanzana phase II Waste Water Treatment Works (WWTW) |
None |
None |
Technical report not yet approved |
Allocated with R5 million |
Selobella Extension 2&3 toilet top structure |
None |
None |
Commenced on 01/07/2015 |
Top structure allocated with R6 million |
Carolina Phase I WWTW |
None |
None |
Will commence on 01/10/2016 |
Top structure allocated with R6 million |
Ekulindeni WWTW |
None |
None |
Technical report not yet approved |
Allocated with R1 million |
Elukwatini WWTW |
None |
None |
Commenced on 01/07/2016 |
Allocated with R7 million |
---00O00---