Refer to Annexure A regarding the progress of the five contracts of Phase II of the Lesotho Highlands Water Scheme.
ANNEXURE A
Contract # |
Description |
Company |
Date of completion |
Tender price (Rand) |
Cost to date (Rand) |
Water Transfer Contracts being implemented |
|||||
2223 |
Project Management Unit |
CDM Smith and Partners |
Dec-2025 |
349 889 571 |
131 625 324 |
3009 |
Professional Services for the Urban Planning, D&S Project Housing & Associated Infrastructure |
Polihali Infrastructure Consultants |
Apr-2021 |
79 365 621 |
14 019 480 |
3014 |
D&S Polihali North Eastern Access Road |
SMEC FMA Joint Venture |
Sep-2016 |
28 453 705 |
4 936 235 |
3015 |
Professional services for the Evaluation, Optimisation, and Site Supervision of Geotechnical investigations |
Jeffares and Green Joint Venture |
Sep-2017 |
19 750 472 |
7 026 482 |
6013 |
RAP PNEAR and site establishment area(in house) |
Inhouse by LHDA |
Jun-2017 |
1 500 000 |
- |
4016 |
Geotechnical investigations-Polihali Tunnel-drilling contractor |
Diabor Pty Ltd |
Aug-2017 |
49 238 075 |
12 515 273 |
Totals |
528 197 444 |
170 122 794 |
D&S = Design and Construction supervision
RAP = Resettlement Action Plan
PNEAR = North East Access Road
D&S = Design and Construction supervision
ESIA = Environmental Social Impact Assessment
RAP = Resettlement Action Plan