(2)(a) The source of delays in the implementation of the entire SRSS were as a result of the change of the Implementation Agent (IA) from the Municipalities (Emfuleni and Midvaal LMs) to Rand Water and secondly, the legal process to cede the service providers from the LMs to Rand Water. However, some of the professional service providers ceding processes experienced legal changes, this involved the Supervising Engineer for the SRSS, which ended up at High Court and subsequently resolved in an out of court settlement.
(2)(b) All the legal processes have been completed and work is currently being undertaken as mentioned in paragraph 1 above.
(3)(a) The implementation of the SRSS will take between 5 to 7 years to complete.
(3)(b) Additional development in both Midvaal and Sebokeng will be connected to both Meyerton WWTW and Sebokeng WWTW, which are being upgraded. Outfall sewer lines are included as part of scope to connect new developments such as Savanna City.
(4) Rand Water is appointed as the IA by the Minister of Water and Sanitation.