(1)(a) The construction of the pipeline will commence in March 2016.
(1)(b) The construction of the pipeline will be completed end of September 2016.
(2)(a) The length will be a 72 km and 350 mm diameter pipeline
(2)(b) 6.5 mega litres per day.
(2)(c) The total cost of the pipeline is R 72 million.
(2)(d) It will be funded by my Department through the Regional Bulk Infrastructure Grant (RBIG).
(3) Yes, the total cost of the project which is R403 million is already budgeted through RBIG in MTEF period
(3)(a) Falls away.
(3)(b) Falls away.
(3)(b)(i) Falls away.
(3)(b)(ii) Falls away.
(4) Yes, the SA National Roads Agency Limited (Sanral) granted approval for servitude.
(5) Falls away.
---00O00---