(1)(a)(i) The budget allocation for the upgrade of Brits Water Treatment Works (WTW) is R60 million.
(1)(a)(ii) The expenditure to date is R36 million.
(1)(b) The first module is envisaged to be completed by July 2016 and overall project completion is August 2018.
(1)(c) The estimated cost for the first module is R 93 million and overall project estimate cost is R800 million.
(2) No, the cost has not increased.
(2) (a) Falls away.
(2) (b) Falls away
(3) The Madibeng Local Municipality is not providing financial support due to financial constraint.
(3)(a Falls away.
(3)(b) Falls away.
(4)(a) The funding is enough to carryover the construction, for the completion of module 1 upgrade.
(4)(b) The construction will be done in phases until completion.