Mr. M. Dlamini presented the project where it was explained that the scope of work was the supply, delivery, installation and maintenance of 16000 solar water heaters to the Ivory Park area. It started on the 11th October 2010 and was completed in 30 April 2012. A total budget of R101.76 million was allocated to the project. Three main contractors were used for the installation Genergy, Thunzi Consulting (Pty) Ltd and Machite Engineering cc. In terms of employment 292 local people were employed on the project as Data Capturers, Community Liaison Officers, Installers and Installer assistants. Roshcon was employed to conduct random audits to selected areas and the SANAS 10106 specification was used to develop a checklist for technical audits. Eskom indicated that there was a 5 year after sales service and maintenance programme and all SWH's have a 5 year guarantee and within this period all the installed geysers will be replaced and/or maintained depending on the defects.