. Umngeni (Khayelisha) consisted of 1 575 units. The project required an upgrade of the Mphophomeni sewerage works in order to accommodate phases 2 and 3 of the project. DFA Tribunal made part of the ROD for only phase 1 to proceed. Phase 2 and phase 3 were intended for an upgrade. The entire project required R40 million. The project site was assigned to the contractor on 19 January 2011 and the civil infrastructure construction was currently in progress.