- The purpose of the project was to provide FIFA with a training venue as a guarantee for the 2010 World Cup. - The project was for the upgrading of the building works inclusive of: VIP building, caretaker flat, spectator toilets, change rooms and gate booths. Storm water reticulation, training pitch and pitch fencing, electrical works and field lighting and erection of grandstand. - The project duration was from 19 June 2009 to 20 May 2010 (49 weeks). - The project budget was R21,000,000. - Thirty two labourers were employed in bricklaying, administration and in carpentry. - Training was provided as follows: 11 in bricklaying, 2 in welding, 5 in pitch laying, 6 in electricity installation and lightning, 4 in plumbing, 1 in carpentry, 6 in paving, 8 in tiling, 4 in glazing and 47 in occupational health & safety.