Tlokwe Community Residential Units was reported to have 100 units which were aimed to be completed by July 2012. The delegation was concerned about the number of units that were given to one contractor Toro ya Africa who seemed to fail to built and some houses showed poor workmanship. The developers in the province seemed to be administering everything i.e. beneficiary list management and construction of houses. The delegation requested the provincial department to furnish it with a full report clarifying reasons for the project to delay, the number of units to be constructed and the contractors appointed. The delegation was concerned about the non involvement of NHBRC at the initial stages of the projects. Furthermore, the delegation was concerned about the balance of R18 million in Jakaranda while houses were completed. It was proposed that 30% of work should be given to women and youth contractors. The delegation was concerned about the provision of VIP toilets to farm dwellers whereas the farm owners were utilising waterborne system and that was viewed as some kind of discrimination.