The project was approved on 21 September 2005 for the installation of Internal Services and the construction of 1000 housing units at Mothutlung Ext 2, within the jurisdiction of the Madibeng Local Municipality. Two show houses were built and during the construction phase the Council was notified that there were no bulk services in the area and MIG funding was applied for and approved. Proconse Consulting Engineers were contracted by Madibeng Local Municipality in 2011 as Project Managers for the installation of bulk services. The engineers have struggled to complete installation of bulk services up to now. Tranche payments were made to the Municipality for the installation of internal water and sewer connections. The contract was subsequently ceded to Homes 2000 (Pty) Ltd by the Municipality. The construction of top structure has started but cannot be completed due to the unavailability of bulk services. The developer has completed the internal services and awaiting bulk for internal connections. Presently the project has registered 927 wall-plates. The wall plates are waiting for completion. The developer cannot complete the houses because beneficiaries cannot move into the houses without ablution facilities, which will create a health hazard. The completion of these houses may also lead to illegal occupation of these houses whilst awaiting completion of bulk services installation.