(1)With reference to Eskom’s De Wilge Residential Development Project in respect of which the costs ballooned from R160 million to R840 million, what
(a) Are names of the service providers who were contracted to build the flats and
(b) Is the breakdown of the amount that was paid to each of them;
(2) Whether anyone has been held accountable for the wasteful expenditure; if not, why not; if so,
(a) Who and
(b) What action was taken against them? NW1002E