(1) No remedial action will be taken against the farmers as the beef and sheep abattoir construction project has not been cancelled but the contract with the appointed contractor was terminated due to challenges experienced in the project. After the contract was terminated, the Department of Agriculture, Land Reform and Rural Development (DALRRD) handed the project to the Eastern Cape Development Corporation (ECDC) to assist with the implementation. A Service Level Agreement (SLA) between DALRRD and ECDC was signed in May 2020 and work is in progress.
(2) No; the construction of the abattoir will continue. ECDC has appointed a Consultant to resuscitate and bring the project to completion. The Consultant is busy with the Condition Assessment and Cost Report to complete the project. A termination account will be concluded, and the contractor will be referred to termination penalty clauses as per the SLA.
(a),(b) Falls away.