With reference to his State of the Nation Address on 10 February 2022, wherein he acknowledged how load shedding was harming the economy and the society and listed several new energy generation projects that he said would be coming online over the next few years, (a) what is the status of each project and (b) by what date can the Republic expect the energy to come online, with particular reference to the
(i) over 500 MW from the remaining projects in Bid Window 4 of the Renewable Energy Programme (REP), which are at advanced stages of construction,
(ii) 2 600 MW from Bid Window 5 of the (REP), for which the preferred bidders were announced in 2021,
(iii) up to 800 MW from risk mitigation power projects that are ready to proceed,
(iv) 2 600 MW from Bid Window 6 of the REP, which was to be opened soon,
(v) 3 000 MW of gas power and 500 MW of battery storage, for which requests for proposals were to be released later in 2022,
(vi) estimated 4 000 MW from embedded generation projects in the mining sector and
(vii) approximately 1 400 MW that was already in the process of being secured by various municipalities?