The Department currently has 14 large water projects running across different provinces. A total of 10 infrastructure projects are under planning, whilst 4 are in construction phase. In terms of progress, 11 projects are behind schedule. Details are tabulated below:
(1) PROJECTS PER PROVINCE |
(2) PROJECT PHASE |
(3) PROJECT SCHEDULE |
||||
Province |
Number of Projects |
Name of Project |
(a) Planning |
(b) Construction |
(a) Behind Schedule |
(b) How Far Behind Schedule |
Eastern Cape |
5 |
Gcuwa Weir |
X |
|
No |
N/A |
Mzimvubu Water Project |
|
X |
Yes |
N/A |
||
Lusikisiki Zalu Dam |
X |
|
Yes |
1 Year |
||
Coerney Dam |
X |
|
No |
N/A |
||
Foxwood Dam |
X |
|
Yes |
1 Year |
||
Free State |
0 |
- |
- |
- |
|
|
Gauteng |
0 |
- |
- |
- |
|
|
Kwa-Zulu Natal |
4 |
Raising of Hazelmere Dam |
|
X (Complete) |
No |
N/A |
uMkhomazi Water Project |
X |
|
Yes |
4 years |
||
Cwabeni Off-Storage Channel Dam |
X |
|
Yes |
9 months |
||
Stephen Dlamini Dam |
X |
|
Yes |
9 months |
||
Limpopo |
4 |
Raising of Tzaneen Dam |
|
X |
Yes |
28 months |
ORWRDP: Olifants Management Model |
X |
|
No |
N/A |
||
New Nwamitwa Dam |
X |
|
Yes |
7 Years |
||
Mokolo Crocodile River (West) Augmentation Scheme - Phase 2A |
|
X |
Yes |
3 years |
||
Mpumalanga |
0 |
- |
- |
- |
|
|
Northern Cape |
0 |
- |
- |
- |
|
|
Northwest |
0 |
- |
- |
- |
|
|
Western Cape |
2 |
Raising of Clanwilliam Dam |
|
X |
Yes |
3 years |
Berg River-Voelvlei Augmentation Scheme |
X |
|
Yes |
6 months |
||
TOTALS |
14 |
10 |
4 |
11 |