Prov |
Project Name |
(a) Details of the contractor allocated to the project within the past two financial years** |
(b)Corresponding contract values of each project in each province |
|
EC |
1 |
Qatywa Lodge |
** |
R32,802,163.00 |
2 |
Western Tembuland Lodge |
** |
R23,437,638.25 |
|
3 |
Maluti Hiking and Horse Trail |
** |
R18,160,388.15 |
|
4 |
Mthonsi Lodge |
** |
R31,072,567.60 |
|
5 |
Nyandeni |
** |
R19,023,014.80 |
|
FS |
1 |
Qwa Qwa Guest House |
** |
R21,120,795.06 |
2 |
Vredefort Dome Interpretation Centre |
** |
R24,160,892.96 |
|
3 |
Monontsha Access Road |
** |
R6,726,894.01 |
|
KZN |
1 |
Isibhubhu |
** |
R29,918,570.53 |
LP |
1 |
The Oaks |
** |
R25,807,207.29 |
2 |
Ngove |
** |
R29,988,483.30 |
|
3 |
Tisane |
** |
R27,463,083.70 |
** Based on the reply to Question 1640 regarding the reasons of not completing projects the POPIA Act is also applied in this case.
** Application of the POPI Act
Protection of Personal Information Act 4 of 2013(c) an assessment of the impact of the completed projects on the (i) overall performance of the tourism industry and (ii) regional economies in the Republic; if not, why not, in each case; if so, what are the relevant details in each case
I have been informed by the Department that the projects are in the construction stage, none of the above-mentioned projects are completed.
I have met with DBSA to discuss the poor performance and advised the Department to establish a project management unit to conduct oversight.