The Department received the Engineers report for the reconstruction of the collapsed roof. The new construction of the roof was not on the initial scope of work for the Repairs and Renovations project that is currently underway in Potchefstroom Magistrate’s Court.
The Department invited quotations from roof specialists for the construction of the roof and the variation order application was submitted to the Variation Order (V.O.) Committee for consideration and upon approval of the V.O, the remedial work will start to reconstruct the roof.
NATIONAL ASSEMBLY: QUESTION NO. 1508 (Written Reply) Ms S J Graham (DA) asked the Minister of Public Works and Infrastructure: |
The draft reply to Parliamentary Question No. 1508 (Written Reply) is submitted for your consideration.
The input has been provided by the Construction Project Management Branch.
I hereby attest that the information provided in response to NA PQ 1508 is true and correct, to the best of my knowledge.
________________________
MR. R MATLALA
REGIONAL MANAGER: MMABATHO REGIONAL OFFICE
DATE:
I hereby attest that the information provided in response to NA PQ 1508 is true and correct, to the best of my knowledge.
________________________
MR. C LOMBAARD
DEPUTY DIRECTOR GENERAL: FACILITIES MANAGEMENT
DATE:
Draft reply supported / not supported/ comments
________________________
MS. N MAKHUBELE
ACTING-DIRECTOR GENERAL
DATE:
NATIONAL ASSEMBLY: QUESTION NO. 1508 (Written Reply) Ms S J Graham (DA) asked the Minister of Public Works and Infrastructure: |
Draft reply supported / not supported/ comments
_____________________
MS. B SWARTS, MP
DEPUTY MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE
DATE:
Draft reply approved / not approved/ comments
__________________________
MR. S ZIKALALA, MP
MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE
DATE:
MINISTRY
PUBLIC WORKS AND INFRASTRUCTURE
REPUBLIC OF SOUTH AFRICA
Department of Public Works l Central Government Offices l 256 Madiba Street l Pretoria l Contact: +27 (0)12 406 1627 l Fax: +27 (0)12 323 7573
Private Bag X9155 l CAPE TOWN, 8001 l RSA 4th Floor Parliament Building l 120 Plein Street l CAPE TOWN l Tel: +27 21 402 2219 Fax: +27 21 462 4592
NATIONAL ASSEMBLY
WRITTEN REPLY
QUESTION NUMBER: 1508 [NW1751E]
INTERNAL QUESTION PAPER NO.: 15 of 2023
DATE OF PUBLICATION: 05 MAY 2023
DATE OF REPLY: MAY 2023
1508. Ms S J Graham (DA) asked the Minister of Public Works and Infrastructure:
What progress has been made to date with implementing the necessary repairs to the roof of the Potchefstroom Magistrate’s Court that partially collapsed in September 2022? NW1751E
REPLY:
The Minister of Public Works and Infrastructure
The Department received the Engineers report for the reconstruction of the collapsed roof. The new construction of the roof was not on the initial scope of work for the Repairs and Renovations project that is currently underway in Potchefstroom Magistrate’s Court.
The Department invited quotations from roof specialists for the construction of the roof and the variation order application was submitted to the V.O. committee for consideration and upon approval of the V.O, the remedial work will start to reconstruct the roof.
__________________________
MR. S ZIKALALA, MP
MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE
DATE: