(1) Whether an environmental impact assessment was completed before work by the Department of Public Works (PWD) commenced on the marine base for 4 Reconnaissance Unit at Salamander in the Western Cape; if not, why not; if so, what are the relevant details; (2) whether her department will stop work on this project until the PWD complies with all the relevant environmental legislation; if not, what is the position in this regard; if so, what will be done about it; (3) whether she has been informed that the contractor working for PWD is dredging without an environmental authorisation; if not, what is the position in this regard; if so, what steps will be taken as a result; (4) whether any notices of noncompliance have been issued against any (a) contractor or (b) PWD regarding work on this site; if not, why not; if so, what are the relevant details; (5) whether any official has been on site to monitor developments since the commencement of the project; if not, why not; if so, on what dates?