The PICC reported that the total cost of ASIDI's committed projects which included new schools and services (e.g. water, sanitation and electricity) to existing schools was R6 billion. As of December 2012, R590 million of this allocation had been spent. By the end of March 2013, R943 million had been spent. A total of 49 schools were rolled out in the Eastern Cape since 2011/12 and 202 school projects for 2012/13 were at different stages in the implementation planning stage. Of the 49 schools, 10 had been completed while 39 were still under construction by December 2012. By the end of March 2013, 22 schools had been constructed while 27 were still under construction.