. Over 86% of contract period has lapsed and the programme was behind schedule on all of the schools; . Contractors were being scheduled by between 75 and 151 days based on their baseline programmes; . Progress at 6 of the schools was between 10.1% and 20%; . Progress at 8 of the schools was between 20.1% and 30%; . Progress at 14 of the schools was between 30.1% and 40%; . Progress at 9 of the schools was between 40.1% and 50%; . Progress at 8 of the schools was between 50.1% and 60%; . Progress at 3 of the schools was between 60.1% and 70%; . Progress at 1 of the schools was over 70.1%; and . Contractual provisions have been invoked for non-performing contractors.