The Committee noted with concern that there was a problem with regard to the progress of the ASIDI programme in the Province. Of concern to the Committee was the fact that not even one of the 49 schools for the 2011/12 financial year had been completed let alone the target of 50 schools for the 2012/13 financial year. The Committee further questioned the credibility and reliability of the Department's revised commitment of achieving a target of 12 schools, instead of the earlier target of 5, by or before the end of August 2012. Of greater concern to the Committee was the fact that, by the time of reporting, only 20 days was remaining before the end of August 2012; hence the completion of 12 schools was deemed unattainable. The Committee expressed serious concern about the poor planning with regard to the ASIDI programme and reference was made to the fact that contractors were yet to be appointed to commence the construction of 50 schools for the 2012/13 financial year.