. Delays in the implementation of water service projects such as Nandoni pipeline, Hluhluwe and Inyaka because approval took longer than had been anticipated; . Payment of R20 million that could not be made before the cut-off date for the Moutse Bulk Water Supply; . Capacity constraints due to the delays in implementation of Occupation Specific Dispensation (OSD) posts; and . Non-delivery of material for the regional bulk infrastructure projects.