Phases 3 and 4 of the Inyaka Water Treatment Works had a contract price of R427 million of which R115 million had been allocated for the 2011/12 financial year. An expenditure of R244.4 million or 57 per cent of the total budget was recorded at the time of the visit from the commencement date of the contract which was 1 September 2008.