With respect to backlogs, the MBLM reported that Vision 2012 of Electricity Universal Access and 2014 of Passable and Trafficable Road Network may not be achieved. The MBLM argued that the latter is mainly due to slow process in appointing a service provider to quantify access roads backlog. Furthermore, the MBLM reported that it has capacity constraints because it is unable to attract people with requisite skills. The MBLM further reported that competing with well-established municipalities for resources (namely: plant hire, service providers etc) is a huge challenge because funding is not enough. With regard to electricity, the MBLM said that it does not have a dedicated unit for electricity and electrification projects are outsourced and not monitored.